Court dispute between third parties regarding the use permits of Purtse wind farm

By order of 21 December 2023, the Tartu Administrative Court decided to hear the complaint of a third party, Eesti Ühistuenergia OÜ, against Lüganuse municipality. The applicant seeks the revocation of the use permits of Purtse wind farm granted to Enefit Wind Purtse AS. The court granted the applicant interim relief, according to which the capacity of the Purtse wind farm must be limited to 3 MW per wind turbine (a total of 5 x 3 MW instead of the installed 5 x 4.2 MW).
Sven Kunsing
Head of Finance Communications
[email protected]
https://enefitgreen.ee/en/investorile/
(GlobeNewsWire)